Article 47 If a project must be subject to tender according to law, the tenderer shall, within 15 days following the date of determining the winning bidder, submit a written report about the tender and bid to the relevant department for administrative sup
Article 47 If a project must be subject to tender according to law, the tenderer shall, within 15 days following the date of determining the winning bidder, submit a written report about the tender and bid to the relevant department for administrative sup
第四十七条依法必须进行招标的项目,招标人应当自确定中标人之日起十五日内,向有关行政监督部门提交招标投标情况的书面报告。